|
DIA Officials Taking Cautious Approach
to Construction
While passenger growth at Denver International
Airport continues its record pace, officials at the 10-year-old
airport are still on a wait-and-see approach when it comes
to construction.
With 60 percent of DIA passengers flying on bankrupt airlines,
caution is the order of the day, said Mike Steffens, assistant
deputy manager of aviation for construction.
"We'd like to keep building things and making them better,"
Steffens said. "But if we're missing a major partner
tomorrow that's going to have a big impact on everything."
Steffens' remarks were made as part of "DEN at Ten,"
a presentation he made to the Construction Management Association
of America's Colorado chapter last Friday - the same day DIA
officials announced that January set a 14th-consecutive monthly
record for passenger traffic.
In 2004, 42.4 million passengers traveled through the Jeppesen
Terminal's three modules, designed to accommodate an annual
load of 50 million passengers.
"We'll be hitting 50 [million] in the next two or three
years, and we can have six modules at full build-out,"
Steffens said.
The airport has no definite plans at the moment for expanding
the concourses, adding new runways - it currently has six
but can handle 12 - or building an airport hotel.
"There's no schedule really [for building the hotel],"
Steffens said. "We want to see if we can get it down
to a cost that's more palatable to our accountants."
Two projects worth approximately $10 million that were recently
open for bids have been postponed - reroofing Concourses B
and C to replace the brittle, first-generation material that
creates the airport's distinctive tented look.
"As long as we don't get hit with a hailstorm, we're
OK," said Steffens. "But one of these days we'll
see [the projects] back on the street."
A couple of projects are either set to begin or under bid
review. They include the Whiskey Alpha De-Icing Pad, a $29
million project awarded to Interstate Highway Construction
Inc. that's set to start in six weeks and Pikes Peak Parking
Expansion Phase II, estimated to cost between $6.25 to $7
million and scheduled to begin in two months.
The contract for the 2005 Miscellaneous Roadway and Parking
Lot Improvements 2005, budgeted between $2.5 to $3.5 million,
is still open for bid.
In Other CMAA News
The Colorado chapter of the Construction Management Association
of America will host the national 2005 spring conference -
"Creating Collaborative Teams" - May 23-24 at the
Grand Hyatt Denver.
Conference highlights include:
- A golf outing at Arrowhead Golf Club and tour of the Denver
Art Museum expansion project.
- Six education sessions on topics like "Evolving
CM in the Future of LEED Certification" and "Claims
Management Services."
- A keynote presentation by Bill Van Wagenen Jr. CCM, of
CH2M Hill, who has worked on such high-profile projects
as the English Channel Tunnel and the Petronas Towers in
Malaysia. He'll discuss public works projects in Iraq.
- And a town meeting on "The State of CM/PM Training:
Is Our Profession at Risk?" with moderator Mike Dell'Isola,
PE, CVS, FRICS.
Early registration - $495 for members - ends March 28. Standard
registration costs $550 for members and runs through April
25. Onsite registration is $595. Reduced registration fees
are available for additional corporate members, owner members,
full-time academic members and speakers.
For more information, visit the Web site at
http://cmaanet.org.
The Colorado chapter's next meeting will be on April 8 at
the Holiday Inn Select Cherry Creek.
Click here for
more Features >>
|