|
CDOT Announces Summer Construction Plans
I-25 Broadway Viaduct set for completion;
$24M in resurfacing scheduled in Denver
Another summer of highway construction is beginning at the
Colorado Department of Transportation, one that will include
a variety of road work ranging from paving to bridge replacements
to interchange improvement projects.
This summer CDOT will have a minimum of 25 construction projects
in the Denver metro area alone, totaling approximately $125
million - not including the $1.67 billion T-REX Project, which
finishes this fall.
"As is usually the case, warm weather means that a good
portion of CDOT's summer construction will focus on resurfacing
as we try to maintain our current system," said CDOT
Executive Director Tom Norton. "However, several of our
projects this season will focus on intersection improvements,
as well as other improvements in an effort to improve safety
despite ever-increasing traffic volumes."
Resurfacing Projects
More than $24 million in resurfacing projects will be under
way in the Denver metro area this summer, including:
- Colorado Boulevard from Martin Luther King Boulevard
to Vasquez Boulevard;
- Colorado Boulevard from Hampden Avenue to Buchtel Boulevard;
- I-25 from 84th Avenue to 120th Avenue;
- Broadway from 58th Avenue and S.H. 224;
- I-76 from south of Bromley Lane to Lochbuie;
- S.H. 93 from South Boulder Diversion Canal to Wadsworth
Boulevard;
- U.S. Highway 6 (6th Avenue) from Simms Street to U.S.
Highway 40;
- C-470 from Morrison Road to Belleview Avenue;
- Wadsworth Boulevard from C-470 to Waterton Road;
- Belleview Avenue from Broadway to University Boulevard;
- Hampden Avenue from Yosemite Street to Parker Road;
- S.H. 7 from York Street to U.S. Highway 85.
New Projects
In addition to the 12 resurfacing projects, six new projects
have recently started or will begin soon:
- I-70 from Brighton Boulevard to Vasquez Boulevard - This
is one of several projects that will repair and replace
expansion joints on this 40-plus-year-old viaduct. Twelve
expansion joints will be repaired or replaced as part of
the $2.6 million project, which started in early April.
Work will continue through October.
- Speer Boulevard at Interstate 25 - This project will
modify the interchange at Speer Boulevard to eliminate the
loop ramps on the west side of I-25. A new ramp will also
be constructed that takes motorists off I-25 to access Invesco
Field. The bridge rail will also be repaired along Speer
Boulevard. The $6.6 million project - mainly funded through
federal funds and by the City and County of Denver - will
begin later this month and continue through August 2007.
- 120th Avenue at Wadsworth Boulevard - This project will
realign and reconstruct the 120th Avenue/Wadsworth Boulevard
intersection. The intersection will be realigned to the
south to increase the distance to the U.S. Highway 36 interchange
to accommodate future construction.
- The reconstruction will add a turn lane from eastbound
120th Avenue to northbound Wadsworth Boulevard and from
northbound Wadsworth Boulevard to westbound 120th Avenue.
Auxiliary lanes will also be added to and from Highway 36.
The $3.9 million project will begin in May and continue
through August 2007.
- Wadsworth Boulevard at Grandview Avenue - This $32 million
project will construct a grade-separated intersection, and
rotomill and pave Wadsworth Boulevard in concrete. Work
will begin in August and finish in July 2008.
- Parker Road from I-225 to Lehigh Avenue - This $1.3 million
project will replace the current raised median with concrete
barrier. The work will take place August through October.
- I-25/U.S. 36/I-76/I-270 - This $15 million project will
construct a flyover ramp from eastbound I-270 to eastbound
I-76. This final phase completes one of Colorado's 28 strategic
projects. The project will start in early fall and finish
in spring 2008.
Continuing Projects
Several projects that were under way last summer will continue
into this construction season, with three of them wrapping
up this year:
- Parker Road at Quincy Avenue - This project widened Parker
Road and eastbound Quincy Avenue to accommodate a third
left turn lane from southbound Parker Road to eastbound
Quincy Avenue. Parker Road from Lehigh Avenue to East Rice
Place was also reconstructed in concrete.
- The realignment was completed on Saturday and all three
lanes of northbound and southbound Parker Road opened in
addition to the third left turn lane from southbound Parker
Road to eastbound Quincy Avenue.
- "This segment of Parker Road near Quincy Avenue gets
extremely busy during the peak hours, and motorists will
be thrilled to see it back into its final configuration,"
said CDOT Project Engineer Mark Meyers. "[They] will
again have a third through lane in each direction, as well
as an additional turn lane, which should really help the
flow of traffic."
- The $3.5 million project will finish by the end of this
month as crews complete work in the median.
- I-25 at 120th Avenue - This project is replacing the
120th Avenue bridge with one that is 70 ft wider and 50
ft longer. The new bridge will accommodate three through
lanes and two left turn lanes onto I-25 in each direction
of 120th Avenue. Both the eastbound and westbound 120th
Avenue structures are complete and work is under way to
lower I-25. The $18.4 million project will finish in July.
- Colorado Boulevard over Vasquez Boulevard - This project
replaces the existing 45-year-old bridge with one that is
slightly wider to accommodate wider shoulders; no extra
lanes will be added. Major construction of the new bridge
is complete and traffic will be switched at the end of May
or early June. The $8.8 million project will be complete
in July.
- I-25 Broadway Viaduct - This $28 million project continues
construction to replace the worst bridge in the state highway
system. The southbound structure is complete and construction
of the northbound structure is nearing completion.
Before completion in July, crews need to pave the new bridge
deck, install guardrail and place traffic into its final configuration.
When complete, four lanes will be open in each direction as
well as all ramps.
High Country Cone Zones
Travelers in the high country will also experience cone zones
along I-70 West:
- I-70 from Empire Junction to Fall River Road and eastbound
I-70 west of the Eisenhower Tunnel (milepost 206-210) -
Both projects will resurface I-70 and require lane closures
in the day and some evenings. The project between Empire
Junction and Fall River Road is under way and will be complete
in August. The I-70 project west of the Eisenhower Tunnel
will take place in June.
- I-70 Ramp Metering - This $2.1 million project installs
ramp meters at three eastbound on-ramps to I-70: I-70/U.S.
40 (Empire Junction), I-70/Downieville and I-70 Idaho Springs
East interchanges. The project will also extend the acceleration
lanes at these locations. Work will begin later this month
and continue through the end of August.
- I-70 Eisenhower Tunnel to Bakerville - This $4.8 million
project installs cable guardrail in the median of I-70,
repairs pipes and paves the eastbound and westbound bore
of the tunnel. Work will begin later this month or early
May and continue through October.
"We recognize that construction projects, big and small,
can still have an impact on travel and cause delays for motorists,"
Norton said. "A recent survey indicates that a large
majority of Front Range and Denver metro area residents prefer
construction and maintenance work be done at night. Wherever
possible, we will schedule night work, but our limited construction
season may also require some day work during non-peak travel
times.
"We'll do our best to minimize delays and inconvenience,
but urge motorists to plan ahead so they won't be caught in
a cone zone if they don't have time to spare."
Click here for
more Features >>
|