|
Flying High
Colorado's Mountain Airports Expanding to Keep Up with Seasonal Growth
Some of Colorado's busiest mountain airports are getting
new facilities, safety improvements and much-needed paving
upgrades this year.
Eagle County
The Eagle County Airport - the closest one to the booming
Vail Valley - has recently seen a big increase in air traffic.
During the winter months, United, Delta, American, Continental
and Northwest Airlines all provide non-stop jet service between
Eagle and 12 major cities.

American introduced daily non-stop flights between Dallas-Ft.
Worth and Eagle this past summer, connecting it with 27 airports,
including the one in Zurich, Switzerland.
According to the airport authority, more than 146,642 flights
have left the Eagle airport so far this year.
However, one of the most important pieces of the airport's
infrastructure - the control tower - was in need of a major
upgrade before bigger jets and more air traffic could be brought
into Eagle.
To position the airport for growth and respond to market demand,
the Eagle County Commissioners and Shaw Construction LLC broke
ground on April 22, 2003 on a new control tower, which was
completed this November.
The old airport tower stood only 43 ft tall while the new
tower is 115 ft tall, and as high as 130 ft, including systems
installed on the roof. The new tower sits on a 31-ft by 31-ft,
three-and-a-half ft thick concrete foundation. All of the
precast for the tower was erected in nine days, from foundation
up to the cab - or control room - at the top.
Shaw Construction Project Manager Dave Hall said that the
high winds in the area - sometimes as stiff as 30-35 knots
- were a major concern during precast erection, especially
in the spring when most of the concrete work was done.
Stresscon Corp. was the precast contractor, and "they
did a great job," Hall said. "The county hadn't
done much in the way of detailed budgeting on the project
before they hired us, and working with Stresscon, we saved
them about 12 percent on the job through value-engineering."
The tower has one elevator that goes up to the eighth floor;
then internal stairs wind up another one-and-a-half levels
to the cab. All of the computer systems to run tower flight
control functions were placed between the eighth level and
the cab, with two levels of offices below that for future
use by FAA officials.
According to Hall, construction on the new tower took only
about six months, with the project expected to finish three
weeks early. "People thought we were nuts even to attempt
to build this tower in that kind of time frame," Hall
said. "Even the designer, who does control towers all
over the country, said they normally take at least seven to
eight months to complete."
Shaw's Division Manager Clark Atkinson, who is also a pilot,
said that he has been flying into the Eagle airport for more
than 11 years, before much infrastructure was in place there.
Then in 1996, Shaw Construction completed the Eagle airport
terminal building. It used to be a metal shed, and the previous
tower was "a series of shipping containers welded together
with another metal shed on the top," Atkinson said. The
airport doubled the size of its terminal in 2002, adding another
33,000 sq ft.
"This airport has averaged about 20 percent air traffic
growth per year, so you can see why these infrastructure upgrades
- and especially the tower - were necessary. During the busy
season, Eagle is the number two airport in Colorado - after
DIA," Atkinson said. "You can land 757s in Eagle,
but not in Aspen." The Eagle airport already has a 10,000-ft
runway, also longer than the one in Aspen, he said.
The new tower was built with no money from the federal government,
and is not yet an FAA-controlled flight tower, but the airport
is in the process of negotiating a lease with the FAA, which
is inspecting the tower to establish it as an FAA-controlled
facility. The radar system to meet those standards is already
in place, according to Atkinson.
The contract completion date for the Eagle airport tower was
Nov. 14, but Shaw Construction turned it over to the county
three weeks early, taking only four-and-a-half months to build
it.
The tower was designed by W.E. Payne & Associates of Denver,
which specializes in aviation work.
Aspen-Pitkin County
At the Aspen-Pitkin County Airport - seasonally, the third
busiest airport in Colorado - better traffic flow and FAA
safety standards will be achieved by relocating the major
taxiway 100 ft east of the main runway, according to Carter
& Burgess Senior Project Manager J.D. Ingram, PE.
Carter & Burgess is providing the engineering design and
project oversight.
The taxiway, which is currently 221 ft long, will also grow
to 320 ft in a $6 million paving and facilities expansion
project. Kiewit Western is the paving contractor on the first
of the project's six segments, under way now, with the second
segment up for bid next spring.
The Aspen airport project also includes improved rescue, firefighting
and emergency response facilities, plus additional equipment
storage, Ingram said.
Gunnison County
In Gunnison, the east end of the airport's main runway will
be extended by 500 ft to compensate for its reduced length
on the west end. Gold Basin Road and the nearby river have
confined the expansion of the runway to the west, putting
it into an FAA non-standard status.
The $8.6 million asphalt paving project, designed by Carter
& Burgess and contracted to Grand Junction's United Co.,
will allow the runway to meet FAA standards and provide for
pavement rehabilitation. The project will strip away a layer
of failed pavement, replacing it with a new layer.
Construction starts next April, with the airport closing for
two-and-a-half months from May 2004 to mid-July, but it will
remain open for most of the work after that. Air traffic for
Gunnison will be re-routed through Montrose during the closure.
According to Carter & Burgess Sr. Project Manager Jim
Fluhr, his firm is providing all of the construction management
services and engineering design on the project. The regrading
and drainage components were done by Sema Construction last
year, and United Co. is already onsite crushing material.
The Gunnison airport will also receive a new high-intensity
runway lighting system when the project is complete.
Upcoming or ongoing projects at other mountain airports include
paving work at Front Range, Montrose, Pagosa Springs and Steamboat
Springs.
Click here for
more Features >>
|