|
Dam Near Done
Standley Lake Rehabilitation Project
in Westminster Will Finish Next Spring
The complete makeover of a Westminster
reservoir is nearing completion after more than two years
of hard work by the local construction and design team.
The aging infrastructure of Arvada's Standley Lake is being
replaced or rehabilitated to improve efficiency and safety.
The dam was leaking along the outlet pipes and needed to be
redesigned to meet current flood control standards.
|
The joint venture partnership of R.E. Monks/ASI RCC has been
acting as general contractors on the $31 million Standley
Lake Dam Improvements project. The owners are the Cities of
Westminster, Thornton, Northglenn and the Farmers Reservoir
and Irrigation Co. Engineering work on the project is being
performed by CH2M Hill, GEI and Rocky Mountain Consultants.
Improvements to the lake include abandoning the existing outlet
works, constructing a new outlet works, building additional
downstream earth berms and constructing a new, enlarged spillway.
Seven structures make up the new spillway, which entails around
two million cu yds of concrete.
"Standley Lake was showing some of the same problems
that a lot of the little dams built long ago along the Front
Range are," said R.E. Monks's Steve Antony. "The
whole thing needed to be upgraded to make it more safe and
efficient."
The Standley Lake project is about a $9 million contract for
his company.
The sitework component entailed moving more than one million
cu yds of compacted fill at the rate of about 15,000 to 20,000
cu yds per day, according to Bill Obenchain, project manager
with R.E. Monks. The firm is also putting in about 90,000
cu yds of riprap, which is about 60 percent complete this
month.
The project has also involved some very complex microtunneling,
including - at 1,200 ft long - the longest continuous-bored
72-in. microtunnel in the United States, according to Antony.
Also complete are the new spillway and seven downstream drop
structures.
One of the next big landmark events on the project will be
the turnover from the old outlet works to the new one in January
2004.
The contract completion of the project was set for Dec. 2004,
but it should be done in April 2004.
"This has been a high-profile rehabilitation project,"
Antony said, "and we've had a good relationship with
our joint venture partner all along. It also helped immensely
to have CH2M Hill working with us. Their national reputation
for quality design is well deserved."
Click here for
more Features >>
|