|
Paving the Way Toward Completion
T-REX faces paving challenges and traffic
shifts this summer
by Karl Lueders
The majority of the paving on T-REX
will be completed by the end of the summer, and light rail
testing has also begun between University and Broadway through
the Narrows.
Construction along Denver's Transportation
Expansion Project is moving toward the home stretch, with
the completion for work on Interstates 25 and 225 and the
light rail system still set for fall 2006. But contractors
still face several major challenges through this summer and
fall.
This summer marks the final paving year for the highways,
with more than 50,000 cu yds of concrete and 200,000 tons
of asphalt yet to be laid, said Bill Murphy, project manager
for Southeast Corridor Constructors, the T-REX general contractor.
"The northbound Narrows [the stretch of I-25 between
University and Broadway] is our main focus for paving,"
he said.
While Murphy expects the majority of the paving to be completed
by the end of the summer, the project schedule has extra time
built in to compensate for uncooperative weather.
"The stone-matrix asphalt we use for the final lift
[the final two-in. topcoat] is more susceptible to the weather
than standard asphalt," Murphy said.
The stone matrix must be poured when the ambient temperature
is above 50 degrees. And, since paving is done at night, the
majority of the stone-matrix paving will likely be done over
the summer. "If we pour the concrete and it gets cold,"
Murphy said, "we have to heat and cover it, which just
adds cost to the project."
University Avenue
University Avenue will be a significant traffic bottleneck
around the highway this summer, as the interchange at I-25
and University will change from its temporary diamond layout
to a single-point urban exchange.
"One of our biggest challenges over the next six months
will be reducing University to one-plus-one lanes," said
Larry Warner, T-REX project director. "That started in
April and will go through fall of 2005."
Milestones
In January, T-REX released a statement citing 10 of the major
milestones it would achieve in 2005. One of the 10, the Elati
Light Rail Maintenance Facility, became operational in January
and the first T-REX light rail vehicles arrived the same month.
Light rail testing has also begun between University and Broadway.
One of the major projects on the T-REX list still under way
but nearing completion is the I-25/I-225 interchange, which
SECC has slated for completion this summer. Warner said that
congestion at the interchange was alleviated with the addition
of another lane on the southbound I-225 ramp in February.
"From the traveling public perspective, opening the
southbound I-225 ramp eased the bottleneck. With the one-lane
configuration, there was a grade that forced trucks to gear
down to get to I-25.
Completion of the Colorado and Hampden bridges, slated for
later this spring, will be a watershed mark for T-REX,"
Murphy said. "After we finish work on the Colorado Boulevard
bridge, there shouldn't be any other girder erections on T-REX."
Another 2005 goal for T-REX is the continued construction
of the Lincoln Avenue parking garage. According to Warner,
the vertical retaining walls are up and 1,100 of the 1,700
concrete structures have been cast to be fitted at the site.
Light Rail Work
Before power can be run to the trains, SECC has to shift
I-25 to its final location. Murphy said he expects that upon
completion of paving, they'll be able to move quickly on to
the final portions of the light rail project.
"By the end of this year, we expect to have the entire
overhead contact system and ballast in place," he said.
"Then we can tie the power sources into the light rail."
By September 2006, the contractors need to have completed
integrated testing on the entire light rail system and be
ready to turn over operations to RTD for its pre-revenue testing.
The light rail line is scheduled to open in December 2006.
Click here for
more Features >>
|