Top Projects: Water & Wastewater
|
1. Lone Tree Creek Water Reuse Facility
Centennial
$30 million
Owner: Arapahoe County Water and Wastewater Authority
General Contractor: Glacier Construction Co. Inc.
Architect: Short and Brennan Architects
Engineers: Richard P. Arber Associates Inc., J.F. Sato & Associates, The RMH Group, Russ Sasakura Engineering, Mulhern MRE Inc.
Among the Subcontractors: Big R Construction Co., Ammex Masonry Inc., Guarantee Electric, Horizon Sheet Metal Inc.
Start: June 2006 Finish: April 2009
This project consists of the new construction of a 3.6-mgd biological nutrient removal facility and advanced water treatment reuse facility. |
|
2. Rifle Regional Wastewater Reclamation Facility
Rifle, Co
$26.5 million
Owner: City of Rifle
General Contractor: Stanek Constructors
Architect: JCA Architects
Engineers: SGM Engineering Inc.
Among the Subcontractors: Sturgeon Electric, Browns Hill Controls
Start: Jan. 2008 Finish: Sept. 2009
This project consists of the fast-track design and new construction of a 2.0-mgd wastewater reclamation facility. |
3. Foothills Water Treatment Plant
Denver
$24.3 million
Owner: Board of Water Commissioners, Denver Water
General Contractor: Garney Cos. Inc.
Engineers: Baste Engineering, CH2M Hill
Among the Subcontractors: Ludvik Electric, Big R Construction, Bemas Construction
Start: Dec. 2006 Finish: March 2009
This project includes new 100-mgd chlorine contact basins and new chemical systems as well as modifications to existing plant facilities and site improvements. |
4. Town of Eagle Wastewater
Treatment Plant Expansion
Eagle
$14 million
Owner: Town of Eagle
General Contractor: Weaver General Construction Co.
Architect: Short and Brennan Architects
Engineers: Richard P. Arber Associates, SM&RC Structural Engineers Inc., Russ Sasakura Engineering Inc.
Among the Subcontractors: Martinez Western Constructors, ASCO Masonry, Temcor, Action Air, Inc., Absolute Plumbing, Sturgeon Electric Co., Utility Control & Equipment
Start: July 2007 Finish: June 2009
This project includes a 1.65-mgd expansion of a conventional activated-sludge wastewater treatment plant, including new headworks facilities, new secondary clarifier, new UV disinfection facilities, new solids handling facilities, and modifications to existing secondary treatment facilities. |
5. Canal Importation Ponds & Outfall
Drainage Improvements Project
Fort Collins
$11.5 million
Owner: City of Fort Collins
General Contractor: Garney Cos. Inc.
Engineers: Anderson Consulting Engineers
Among the Subcontractors: Schmidt Earth Builders, Lafarge, Belmire Sprinkler & Landscape
Start: May 2008 Finish: Nov. 2009
The Canal Importation Ponds and Outfall Project was developed following the city council’s 2001 adaptation of the Canal Importation Master Drainage Plan. The project encompasses a network of detention basins and storm sewers to address flooding and water quality problems in west central Fort Collins. |
|