|
Bridge Demolished over Willow Springs Road/Denver Begins Study of Mountain Parks System/Berthoud Pass Widening Completed
The demolition last fall of the bridge over Willow Springs Road in Jefferson County marked the first major phase of construction on a $5.1 million bridge replacement project by the Colorado Department of Transportation. Work is expected to finish next September.
U.S. 285 Bridge Replacements Under Way
The first major phase of construction is under way on the
U.S. Highway 285 bridge replacement project just west of C-470
in Jefferson County.
This fall, crews demolished the northbound U.S. Highway 285
bridge over Willow Springs Road.
Ames Construction Inc. is the contractor for the $5.1 million
project, scheduled for completion by the end of September.
The construction of the new northbound bridges is expected
to take approximately six months. During this phase, U.S.
Highway 285 will remain in its current configuration.
CDOT Starts Work on North I-25 Widening
Work began in the fall on a widening project along a portion
of North Interstate 25 between State Highways 52 and 119 in
Weld County. It is the second widening project along the "North
Forty" corridor - S.H. 7 to Fort Collins - identified
in 1996 as one of the state's high-priority corridors.
This phase of reconstruction and widening - contracted to
Flatiron Constructors Inc. of Longmont for $36 million - includes
safety and capacity improvements between S.H. 52 and S.H.
119 and will add one lane in each direction with a 12-ft shoulder
on the outside and a 15-ft shoulder on the inside.
The frontage roads will also be reconstructed to accommodate
more turn lanes and a 10-ft shoulder, and the Weld County
Road 20 underpass will be reconstructed. This phase begins
nearly two years after CDOT completed the the widening of
a six-mile segment of I-25 between S.H. 7 and S.H. 52, which
was accelerated by five years because of bonding. It is being
funded by state general fund dollars made possible by the
passage of Referendum C, as well as $8 million in federal
funding for the I-25 corridor between Dacono and Fort Collins.
In addition to the current construction project, CDOT is planning
a third project between S.H. 119 and S.H. 66, which will widen
three miles of I-25 from four to six lanes and reconstruct
the S.H. 66 interchange. This project is tentatively scheduled
to begin this spring or summer. The three projects combined
will improve a total of 14 miles of I-25.
The entire North I-25 corridor is also currently undergoing
an Environmental Impact Statement, analyzing potential highway
and transit improvements between Wellington and Denver Union
Station. As part of the EIS, which will be complete in 2008,
three alternatives are being considered:
Package A - Widens I-25 to six lanes with auxiliary lanes
in some locations and includes commuter rail along the U.S.
Highway 287 corridor;
Package B - Adds tolled express lanes in the median of I-25
with bus rapid transit running in the express lanes;
A no-action alternative.
The project is scheduled to be complete by fall 2008.
Denver Begins Study of Mountain Parks
System
Denver Parks and Recreation will begin this month a two-year
master-planning process for its historic 14,000-acre mountain
parks system. The goal of the process is to bring the 1914
vision that originally created Denver Mountain Parks into
the 21st Century.
The system of scenic parks and roads - designed by the Olmsted
Brothers firm in Massachusetts - is listed on the National
Register of Historic Places.
The master-planning process will involve partners from four
other counties, federal and state agencies and residents
in five counties. The lead consultant for Denver Mountain
Parks master plan is Mundus Bishop Design Inc. in Denver.
Other firms working on the project include Andrews and Anderson
PC, The Trust for Public Lands, ERO Resources, Walden Group,
Community Focus, Fehr & Peers and CTM Mapping.
Total funding for the master plan is estimated at $150,000.
Implementation of the plan will be funded by a combination
of private and public dollars.
CDOT Finishes Widening of Berthoud Pass
Federal, state and local officials and citizens celebrated
the completion last fall of the Berthoud Pass Mountain Access
Project - the 14th project finished under TRANS (Transportation
Revenue Anticipation Notes), a bonding program initiated
by Gov. Bill Owens and approved by voters in 1999.
The Colorado Transportation Commission established a statewide
list of 28 Strategic Transportation Projects in 1996, and
proceeds from the bonds advanced those projects.
The recently completed final phase, a $15.6 million project
that widened the lower two miles of Berthoud Pass, began
in 2004 and included adding a climbing lane to the existing
two-lane highway; construction of several retaining walls;
shoulder widening; new snow storage areas adjacent to widened
shoulders; a large wildlife crossing under the highway and
adjacent deer fencing, protecting wildlife and humans; a
new storm-drainage system to keep mountain runoff clean
and separate from highway surface runoff; construction of
four permanent sediment-capture basins to improve water
quality; and 56 new drainage inlets, designed to improve
water management efficiency.
The last major improvement on the east side of Berthoud
Pass was in 1938. Before the recent construction, the road
was as narrow as 25 ft, had minimal shoulders and virtually
no recovery zones for vehicles. Drivers now have three lanes
- two uphill, one downhill - with a width of at least 66
ft and more in some areas.
The Colorado Department of Transportation reconstructed
the upper three miles of the pass between 1999 and 2002
for $50 million.
Park Named after Noted Denver Community
Leader
Denver Parks and Recreation reopened and renamed the park
located in the heart of LoDo's Ballpark neighborhood at
the intersection of Broadway, Lawrence and Park Avenue West.
Edward J. "Eddie" Maestas Park - formerly known
as Broadway Triangle Park - was named to honor Eddie Maestas
(1932-1998), the owner and operator of Johnnie's Market
at 2030 Larimer St. who was known as "the mayor of
Larimer Street."
In addition to its new name, Maestas Park underwent significant
improvements, including the addition of a large plaza with
seating areas and a raised planter with groundcover plantings
and trees.
Following a Denver tradition, street trees will be planted
on all three sides of the park, lighting will be improved
and irrigation will be upgraded. These amenities will support
the area as a public space and will address past maintenance
problems.
City Still Seeking Comments on Civic Center
Park Redesign
The three-dimensional model of ideas for Civic Center Park
created by Studio Libeskind have been moved to the Denver
Public Library, 100 W. 14th Ave. Parkway.
The display, located in the Denver Western History Department
on the fifth floor, will offer the public an additional
opportunity to explore the ideas presented in August by
Libeskind, who was contracted by the Civic Center Conservancy
to develop conceptual ideas for the park.
Libeskind's planning ideas do not represent final designs
but are intended as a starting point to inspire the public's
imagination beyond ordinary solutions, city officials said.
Since Libeskind's ideas were unveiled last summer, Denver
Parks and Recreation and the Conservancy have been hosted
a series of public forums and community discussions, dubbed
"Civic Center Sessions."
Public comments on Civic Center Park are being collected
through an online survey at www.denvergov.org/Planning_Design_and_Constr/template26273.asp.
They will be included in a summary report to the Denver
Parks Advisory Committee this month.
Renovations Close Denver's City Park Lake
Until Next Summer
Public access along several roadways and walkways around
Ferril Lake at City Park in Denver will be closed through
June because of an $18 million renovation project, including
stormwater drainage, asphalt walkway improvements and reconstruction
of the Electric Fountain.
"More than 80,000 cu yds of sediment and soil will
be hauled out of the lake bottom by daily truck loads over
the course of the project. The entire work area encompassing
25-plus acres will be fenced and off limits to park users
because of the extent of dangerous conditions, including
excavated terrain, exposed utilities, trenches, broken pavement,
material stockpiles and frequent disturbances to normal
park conditions.
The renovations will allow for the installation of stormwater
pipes as part of a larger effort to establish a stormwater
detention area in the park. Denver's wastewater management
department plans to improve the lake as a holding basin
where storm runoff will be temporarily stored for short
periods during heavy downpours.
While the bulk of improvements will serve the needs of stormwater
control, other park-related improvements will also be made
to maximize benefits for public enjoyment and park use.
Click
here for more Infrastructure News >>
|