|
Elati Opens, T-REX Light
Rail Vehicles Start Testing
The new Elati Light Rail Maintenance
Facility began operations on Jan. 2.
The 125,000-sq-ft, state-of-the-art facility is where all
of the Regional Transportation District's light rail fleet
will be cleaned, maintained and inspected, including the 34
new vehicles being added to the system through T-REX. Heavy
repairs will still take place at the existing Mariposa Light
Rail Maintenance Facility.
Also, light rail vehicles began testing on part of the T-REX
project in late December.
Through March, empty light rail vehicles will run intermittently
on the tracks from Broadway to Steele to test various elements
of the new system. The track, signals, substations and Overhead
Contact System are among the systems that the design-build
contractor, Southeast Corridor Constructors, is testing to
ensure that the elements are all working together properly.
After the integrated testing is complete next month, RTD
will begin using the same rail segment to test 34 new light
rail cars being provided through T-REX. Each new vehicle must
operate successfully for 1,500 miles before being put into
service.
Periodically for the next two years, empty light rail vehicles
will be running in the segment from Broadway to Steele.
T-REX construction is on schedule for completion in September
2006. The Southeast Corridor Light Rail is on track to open
to the public in December 2006.
Major Milestones Expected
for T-REX in 2005
T-REX is set to hit a number of other major milestones this
year, including:
- The start of construction on
the Lincoln parking garage;
- Completion of the Arapahoe parking
garage and the start of its use as a new park-n-Ride;
- The opening of a highway segment of
Interstate 225 in its final configuration;
- Completion of the Hampden Avenue
Bridge reconstruction;
- Completion of the Colorado Boulevard
Bridge reconstruction;
- The opening of additional lanes in
the Narrows section of Interstate 25; and
- Completion of the final configuration
of the I-25/I-225 interchange.
Some of T-REX's major accomplishments in 2004 included widening
I-25 to five lanes in each direction from Belleview Avenue
to County Line Road; opening three lanes of traffic in each
direction on I-225 from Yosemite Street to Parker Road; opening
the Evans on-ramp to southbound I-25 and northbound off-ramp
at Evans; opening the tunnel for traffic traveling from southbound
I-225 to southbound I-25; and completion of the Elati Light
Rail Maintenance Facility.
CDOT Covers Experimental Pavement on I-70
CDOT covered a section of experimental asphalt pavement on
westbound I-70 in December due to safety concerns. The pavement
will be permanently removed and replaced next spring.
As part of its ongoing testing of new products, CDOT installed
a 2,000-ft-long experimental section of new asphalt pavement
on westbound I-70 between the Buffalo Herd Overlook and Chief
Hosa exits.
The pavement - known as open-graded friction course - has
been used in some European countries and shown to have noise-mitigating
qualities.
However, due to weather and roadway characteristics in the
area - such as inclines and curves - the pavement instead
resulted in reduced skid resistance and increased accident
potential.
The cost to install the test pavement was $52,000. The expected
cost to cover and ultimately replace the OGFC is between $40,000
and $50,000.
Contractor Repairs Damage Caused by Massive
I-70 Rockfall
The Colorado Department of Transportation and contractor
Kiewit Western Co. of Littleton repaired the damage caused
by the Thanksgiving rockslide on Interstate 70 in Glenwood
Canyon, working through late January to fix the slide zone
- an area just west of the Hanging Lakes Tunnel.
The $1 million project included repairing eight damaged sections
of bridge deck in the eastbound lanes and roadway damage on
the westbound lanes. It required significant removal and replacement
of asphalt pavement.
Engineering Design Change Proposed for Lowry
Landfill
The City and County of Denver and Waste Management of Colorado
Inc. have asked the Colorado Department of Public Health and
Environment to review an engineering design and operations
plan that would increase the slope of the cover on Section
6 of the Lowry Landfill Superfund Site.
The change was requested to improve surface water drainage
and prevent water penetration or accumulation at the site,
located at 2500 S. Gun Club Rd. in Aurora.
Lowry Landfill - also known as the Denver Arapahoe Disposal
Site - is not the location currently used for waste disposal
nor is it associated with the former Lowry AFB. in Denver
and Aurora.
The plan proposes to increase the slope of the four-ft-thick
cover on the existing landfill in order to improve surface
water drainage and prevent water penetration or accumulation
on the cover.
Under this proposal, the slope of the landfill cover would
be increased to roughly five percent by removing and stockpiling
two ft of the existing cover and by then placing an additional
5.6 million cu yds of inert material and construction and
demolition debris on top of the landfill.
The cover then would be replaced and reconstructed.
No municipal solid waste disposal is proposed and only limited
industrial waste would be accepted and approved for disposal
on a case-by-case basis. The disposal of inert materials -
limited to construction materials such as masonry, concrete,
brick and rock - could continue for seven to 14 years, if
approved.
Click here for
more Infrastructure News >>
|