|
Colorado Limits Construction Defect
Claims
By Janet Lawler McDaniel
Faegre & Benson LLP
Contractors and subcontractors in Colorado will begin to
see some relief from claims for damages because of alleged
construction defects now that the legislature has passed the
construction defects bill. The new law preserves the ability
of owners to recover actual damages but limits the amount
of treble damages and attorneys' fees recoverable.
The highlights of the bill, which applies to all lawsuits
filed after April 25, 2003, are summarized in this article.
Who Is Protected?
The statute limits claims for damages against "construction
professionals," defined to include "an architect,
contractor, subcontractor, developer, builder, builder vendor,
engineer or inspector performing or furnishing the design,
supervision, inspection, construction or observation of the
construction of any improvement to real property." If
the improvement involves commercial property, "construction
professional" also includes any previous owner of the
property at the time the work was performed.
What Is Included?
The new law applies to both residential and commercial property.
It applies to a civil lawsuit - as well as an arbitration
- seeking damages, indemnity or contribution against a construction
professional caused by a defect in the design or construction
of an improvement.
What Is the Process?
The Notice of Claim process in the statute requires the claimant
to provide the construction professional with written notice
of the alleged defects and damages, access to the property
for inspection and an opportunity to repair the alleged deficiencies.
If the claimant fails to follow the procedure in the statute
and files a lawsuit, the lawsuit will be stayed until the
claimant complies with these requirements.
The notice must describe the "general nature" of
the alleged defects in "reasonable detail" and be
sent to the construction professional 75 days before the claimant
can file a lawsuit - 90 days on commercial projects.
The construction professional has 30 days to inspect the
property and 30 days after the inspection to submit an offer
of monetary settlement, or offer to remedy the alleged defect
with a schedule for completion of the work.
The claimant then has 15 days to accept the offer. If there
is no offer - or if the claimant rejects the offer, or if
the construction professional does not comply with its offer
- then the claimant can file a lawsuit against the construction
professional.
If a written notice of claim is served before the statute
of limitations expires, the limitations period is extended
to 60 days after the conclusion of the notice of claim process.
What Are the Damage Limits?
Damages are limited to "actual damages," defined
as the lesser of the fair market value of the property without
the alleged defect, or the replacement cost of the property,
or the reasonable cost to repair the defect, plus relocation
costs. If the property is residential, costs related to loss
of use, interest and attorneys' fees may be recovered if provided
by contract or by law.
Treble damages could be awarded if the claimant wins on a
claim under the Colorado Consumer Protection Act and the construction
professional's offer before the lawsuit was less than 85 percent
of the actual damages awarded - not including interest, costs
and attorneys' fees; or if the construction professional made
no offer in response to the notice of claim or failed to perform
the terms of an accepted offer.
In any event, even if treble damages and attorneys' fees
are awarded, the maximum limit will be $250,000 beyond actual
damages.
Hopefully, this limit on damage claims for alleged construction
defects will translate into relief for contractors and subcontractors
on the premiums for general liability insurance coverage in
the near future.
-From AGC/C ON Site
State Transportation Commission
Decides to Issue TRANs Bonds
On May 15, the Colorado Transportation Commission unanimously
approved a resolution directing the staff of the Colorado
Department of Transportation to move forward with another
issuance of TRANs bonds to accelerate additional projects
within the 28 Strategic Transportation Corridors.
"Economic conditions for bonding are favorable right
now," said Transportation Commission Chairman Joseph
Jehn. "We've been making great progress on critical transportation
projects all across the state and we'd be remiss not to take
advantage of the bond market to continue improving Colorado's
transportation system."
The Transportation Commission has approved a fiscal year
2004 issuance for approximately $100 million and a follow-up
issuance in fiscal year 2005 for the remainder of bonding
capacity, estimated to be approximately $120 million. The
FY 2005 bonds will be issued only if market conditions allow.
The resolution adopted only the financial plan for bonding.
It did not prioritize projects to be funded with bond revenues.
At their budget workshop in June, CDOT staff will provide
the commission with several scenarios showing which projects
could start construction quickly. At that time, the commission
will decide which projects to fund over the next year.
The state Transportation Commission is appointed by the governor
to set policy and approve CDOT's budget.
Colorado Asphalt Producers Make Significant
Environmental Progress
The Colorado Department of Public Health and Environment
- Air Pollution Control Division has completed a two-year
study of hot mix asphalt production facilities and concluded
that significant environmental progress has been made by Colorado
Asphalt Pavement Association member companies.
Nineteen CAPA-member companies representing 44 hot-mix asphalt
production facilities participated in the study. Chuck Hix
of the state's Air Pollution Control Division said: "The
study - COMPASS project - should be viewed as a highly successful
program. The participants greatly improved both their compliance
rate and their understanding of environmental compliance issues."
Facilities were reviewed for air emissions, water, and pollution
prevention control.
For a copy of the executive summary of the study, go to:
co-asphalt.com/pdf/Exec Summary COMPASS Asphalt Project - Chuck Hix.pdf
Click
here for more News >>
|