|
1. T-REX
Contractor:
Southeast Corridor Constructors (SECC)
Cost:
$1.67 billion - Cost being shared by CDOT ($795 million)
and RTD ($879 million).
Colorado's mega design-build Transportation Expansion (T-REX)
Project is moving at full speed and is on schedule and within
budget. The project is a unique partnership between CDOT,
RTD, the Federal Highway Administration and the Federal Transit
Administration. SECC is the design-build contractor for the
project. SECC began work in October 2001 and is scheduled
to complete the project in fall 2006. The design-build project
is adding 19 miles of light rail transit and reconstructing
and widening 17 miles of I-25 and I-225 in southeast metro
Denver.
2. State Highway 82 - Snowmass Canyon
Contractor: Ames Construction
Inc.
Cost: $100 million
Start Date: Fall 2000
Completion Date: Fall 2004
Snowmass Canyon is the final project to widen State Highway
82 between Glenwood Springs and the Aspen area. Work on the
3.5-mile segment, a smaller version of I-70 through Glenwood
Canyon, includes six bridges and 37 retaining walls. Work
continues on the new up-valley lanes (to Aspen) through fall
2003. The final year of work is the widening and reconstruction
of the new down-valley lanes, the current SH 82.
3. North Forty
Contractor: Edward Kraemer
and Sons Inc.
Cost: $63 million
Start Date: Dec. 2001
Completion Date: Late 2004
A seven-mile stretch of I-25 between State Highway 7 and State
Highway 52 is being reconstructed and widened from four to
six lanes. Additional improvements have been made to the I-25/Weld
County Road 8 interchange, including plans for a new park-and-ride
facility. As of April 2003, the new southbound lanes were
complete and work was under way to finish the northbound lanes.
The reconstruction of this stretch will be completed by late
2004, and additional phases that will widen I-25 from SH 52
to SH 66 will follow when funding becomes available.
I-76/I-270 Phase II and III
Contractor: Hamon Contractors,
Inc.
Cost: $21 million
Start Date: June 2000
Completion Date: June 2003
Phase IV
Contractor: Hamon Contractors,
Inc.
Cost: $8.5 million
Start Date: July 2001
Completion Date: Spring
2003
Multiple phases of this project are currently under way to
improve the I-270/I-76 interchange. The second and third phase
constructs seven new structures at the interchange and rebuilds
the ramp movements from westbound I-270 to eastbound and westbound
I-76. The new ramp movements allow motorists to exit to both
eastbound and westbound I-76 from the right lane and were
functional by June 2003. The fourth phase constructed eastbound
I-270 from I-25 to York Street, including new bridge structures
at I-270 over Washington Street and I-270 over Clear Creek.
This portion of the project was completed in spring 2003.
Interstate 25 - Woodmen Road Interchange
Contractor: Centric-Jones
Co.
Cost: $27.2 million
Start Date: January 2001
Completion Date: December
2003
The reconstruction of this major interchange in north Colorado
Springs includes additional lanes on I-25, new on/off ramps,
additional acceleration and deceleration lanes on I-25 between
North Nevada Avenue and Academy Boulevard and additional through
lanes on Woodmen Road to increase safety and enhance the signal
progression on Woodmen Road between Monument Creek and Campus
Drive. The new southbound lanes are complete. Work continues
on northbound I-25 and on Woodmen Road, east of I-25.
Interstate 25 - Monument Interchange
Contractor: Lawrence Construction
Co.
Cost: $27 million
Start Date: August 2002
Completion Date: Spring
2005
The reconstruction of this busy interchange in north El Paso
County includes new on/off ramps for northbound and southbound
I-25, construction of Jackson Creek Parkway, east of I-25
and south of SH 105 and a new park-and-ride lot. Work continues
on the SH 105 bridge and the new ramp system. Jackson Creek
Parkway is complete.
US 287 Berthoud Bypass
Contractor: Sema Construction
Inc.
Cost: $26.5 million
Start Date: January 2003
Completion Date: 2006
This 5.2-mile project constructs a bypass around the town
of Berthoud that extends from US 287 at Berthoud to just south
of SH 60. Currently, US 287 consists of two lanes with no
turn lanes or acceleration/deceleration lanes. This project
will widen US 287 to four lanes and add turn lanes and accel/decel
lanes that run through the center of town. In addition, four
bridges will be constructed and two intersections will be
improved. The construction of the bypass is the last phase
of a multi-phase project that has improved a 17-mile stretch
of US 287 between Broomfield and Loveland. Previous phases
consisted of widening and capacity improvements along US 287.
Interstate 25 - Nevada Avenue/Tejon
Street Interchange
Contractor: Lawrence Construction
Co.
Cost: $25 million
Start Date: February 2001
Completion Date: Late summer
2003
This interchange reconstruction includes a number of upgrades
that will improve traffic movements in this area of south
Colorado Springs. In addition to increased lane capacity on
I-25, the project includes new on/off-ramps, acceleration/deceleration
lanes between the interchange and the US 24 interchange to
the north, new bridges on I-25 and a new Nevada Avenue bridge
over Fountain Creek. As of April 2003, the northbound lanes
of I-25 were complete, with work remaining on the southern
half of the interchange and the ramp system.
US 160 Wolf Creek Pass
Contractors:- Tunnel Phase
I: Kiewit Western Co. of Littleton for $10.3 million contract
amount, started in October 2000; Tunnel Phase II: ASI, RCC
of Buena Vista for $12.3 million contract amount, started
in April 2003
This tunnel project is the first phase of a multi-phase project
to reconstruct and improve the safety on US 160 on the east
side of Wolf Creek Pass. The tunnel will be open to traffic
in mid-2004. The tunnel projects involve construction of a
900-ft tunnel on Wolf Creek Pass in an area called the Upper
Narrows, about seven miles east of the pass summit. Explosives
were used to blast the tunnel through the mountain; work on
the tunnel this season will include concrete lining, portals,
lighting, emergency and monitoring equipment and roadway realignment.
Remaining safety improvements on this corridor between the
tunnel and South Fork will be scheduled when funding becomes
available.
Ken Pratt Boulevard Extension (SH
119)
Contractor: Castle Rock
Construction Co.
Cost: $11.1 million
Start Date: September 2002
Completion Date: December
2003
This is the second phase of a project that will join two sections
of State Highway 119 through Longmont. Ken Pratt Boulevard
will be extended three miles beyond its current east termination
at US 287 and will connect with State Highway 119 to the northeast.
The extension will consist of three miles of new four-lane
concrete pavement with a bicycle/pedestrian path running alongside,
connecting with the St. Vrain Greenway. The previous phase
constructed four new bridges as well as a concrete box culvert
extension for Dry Creek at US 287.
US 50 Delta to Grand Junction
Contractor for Delta North: Elam
Construction of Grand Junction
Cost: $11.5 million
Start Date: October 2002
Completion Date: 2004
The 34-mile corridor is being widened from two to four lanes.
Three of six phases have been completed with two phases in
progress, and a final phase scheduled to begin in 2006, when
funding becomes available. The most recent segment to get
under way begins at Delta and proceeds north for 5.1 miles
to G-50 Road. This segment is scheduled for completion in
2004. The entire US 50 Delta to Grand Junction corridor is
approximately 70 percent complete.
I-225/Iliff Avenue Interchange
Contractor: Sema Construction
Inc.
Cost: $10.5 million
Start Date: November 2002
Completion Date: Projected
for summer 2003
This interchange improvement project began in November 2002
and will replace the northbound and southbound bridges on
I-225 and will also reconstruct and realign the roadway for
a smoother transition onto I-225. The project will also involve
some safety improvements by adding guardrail, retaining walls,
and fencing at the intersection. AT project completion, westbound
Iliff Avenue approaching I-225 will be wider, and the entire
interchange will consist of new concrete pavement
Broadway Viaduct - Phase II
Contractor: Sema Construction
Inc.
Cost: $9.8 million
Start Date: November 2002
Completion Date: May 2004
The entire project reconstructs the I-25 viaduct over Broadway,
including the replacement of the I-25 bridge over Broadway.
The second phase is currently under way and completes the
remaining portion of the southbound bridge. Once the southbound
portion is complete, traffic will be switched onto the new
structure. The current phase will be completed by May 2004,
leaving only one phase left to finish the northbound portion
of the bridge.
US 160 Treasure Falls to Snow Shed,
Wolf Creek Pass, Phase II
Contractor: Nielson's Skanska
of Cortez
Cost: $7.16 million
Start Date: September 2002
During this phase, work has included rock blasting, improving
the safety and sight distance of the westbound truck ramp
approach, drainage improvements on the top 3.5 miles (including
the snow shed) and final highway rehabilitation and paving
of five miles. The project was mostly complete in October
2002, but some minor work - such as landscaping and snow shed
lighting - was done in spring 2003.
U.S. 85 - State Highway 67 Intersection
Contractor: Ames Construction
Inc.
Cost: $8 million
Start Date: April 2003
Completion Date: April 2004
The reconstruction of the US 85/State Highway 67 intersection
will realign US 85 east of its current location through Sedalia,
increasing capacity and reducing backups on SH 67 for vehicles
stopped at the US 85 traffic light and at the Burlington Northern/Santa
Fe railroad crossing. The current US 85 will become a frontage
road. Other improvements include a new traffic signal, turn
lanes, raised medians and sidewalks and a wildlife tunnel
south of the intersection.
|