1. GE Blue Spruce
Location: Aurora
Cost: $15.1 million
General Contractor: TIC - The Industrial Co
Start Date: June 2002
Completion Date: February 2003
A dual fuel simple cycle facility gas turbine project, utilizing (2)
GE 7FA CT's.
Top
2. Metro High Solids Centrifuges
and Cake Storage Improvements
Location: Denver
Cost: $10.6 million
General Contractor: Western Summit Constructors Inc
Start Date: June 2002
Completion Date: August 2003
The project involved construction of a new four-story dewatered sludge
facility; renovation of the existing dewatered sludge facility; renovation
of three sludge holding tank pump stations and one centrate pumping station;
renovation of the sludge processing building; the installation of four
new high-solids centrifuges procured by the owner; renovation to the belt
conveyor system; and renovation to the electrical, HVAC, plumbing and
hydronic systems.
Top
3. Centerpark Industrial Center
Buildings A & B
Location: Denver
Cost: $9.5 million
General Contractor: DSP Builders Inc
Architect: Intergroup Inc
Start Date: December 2002
Completion Date: December 2003
Two one-story, tilt-up concrete buildings to be used for manufacturing/distribution.
Two additional buildings will be completed in 2004 for a total of four
buildings. Work includes demolition of 'old Keebler site' at 5000 Osage.
Top
4. Roth Distributing
Location: Denver
Cost: $2.49 million
General Contractor: DSP Builders Inc
Architect: Intergroup Inc
Start Date: February 2003
Completion Date: July 2003
42,000-sq-ft tilt-up office/distribution center for Roth Distributing
including all associated site work and office tenant finish.
Top
|