Projects
 Gold Hard Hat Awards 2009
 Top Projects of 2009
 Gold Hard Hat Awards 2008
 Top Projects of 2008
 ABC-EIC Award 2007
 ACEC-CO Awards 08
 AGC of CO ACE 2007
 ASA CO Awards 2007
 CCASLA Names 2007
 Top Projects of 2007
 Gold Hard Hat Awards 2007





Top Projects - Infrastructure

1. Front Range Power Project
Location: Fountain
Cost: $257 million
General Contractor: TIC - The Industrial Co
Start Date: February 2001
Completion Date: June 2003
480 mw combined cycle power plant.
Top

2. Standley Lake Dam Rehabilitation
Location: Westminster
Cost: $30.64 million
General Contractor: ASI RCC Inc
Start Date: July 2002
Completion Date: November 2004
Twin 72" diameter microtunnel wet taps in existing reservoir. Construction of two underwater intakes, a 35-ft diameter reinforced concrete valve shaft 100-ft deep, new spillway with concrete labyrinth weir and multiple drop structures includes 28,000 cu yd of RCC and 7,500 cu yd conventional concrete.
Top

3. Northern Colorado Water Conservancy District Campus
Location: Berthoud
Cost: $12.8 million
General Contractor: FCI Constructors Inc
Architect: RB+B Architects
Start Date: April 2002
Completion Date: June 2003
New 45,000-sq-ft office building; 33,600-sq-ft maintenance building; and three new storage buildings totaling 18,000 sq ft. On a 19 acre site.
Top

4. East Cherry Creek Valley - Western Pump Station
Location: Highlands Ranch
Cost: $8.4 million
General Contractor: Western Summit Constructors Inc
Start Date: August 2002
Completion Date: June 2003
The project involved construction and installation of a new water pump station and associated appurtenances including all earthwork, sitework, civil, yard piping, architectural, mechanical, structural, electrical, instrumentation and control, and dewatering. Also included furnishing and installation of a 42-in and larger discharge pipeline, 36-in suction pipeline, various yard piping, associated isolation valves, various fittings, metering equipment, and furnishing and installation of all I & C equipment necessary for the existing Willow Water Wells and existing above ground storage tanks.
Top

5. Mt Crested Butte Wastewater Treatment Plant
Location: Crested Butte
Cost: $6 million
General Contractor: Garney Companies Inc
Start Date: April 2002
Completion Date: April 2003
Plant expansion from .6 million gal. per day to 1.2 million gal. per day.
Top

6. Crystal Valley Water Storage Reservoir
Location: Castle Rock
Cost: $5.2 million
General Contractor: Garney Companies Inc
Start Date: September 2001
Completion Date: April 2003
Four million-gal. post-tensioned concrete water tank with two pump stations and associated piping.
Top

7. Denver Water Reuse Conduit 301
Location: Commerce City
Cost: $4.1 million
General Contractor: Aisa Civil Inc
Architect:
Start Date: March 2003
Completion Date: October 2003
42-in. steel reused waterline - 13,850 ln ft; 900 ln ft tunnels - 60-in. diameter; 1400 ln ft 42-in. RCP storm drain.
Top

8. Greeley SCB Slurry Wall (Water Storage)
Location: Greeley
Cost: $3 million
General Contractor: Hall-Irwin Construction Division
Start Date: June 2002 Completion Date: January 2003
Approximately 10,000 ln ft of slurry wall construction in Greeley. Excavation was performed to depth of 63 ft and keyed into the bedrock.
Top

9. Pleasant View Sanitary Sewer Outfall
Location: Lakewood
Cost: $2.3 million
General Contractor: Aisa Civil Inc
Start Date: April 2002
Completion Date: May 2003
11,000 ln ft of 24-in. PVC gravity sewer; 1,300 ln ft of 42-in. tunnels.
Top

10. Ute Pass Water Treatment Plant Phase 2 Expansion
Location: Green Mountain
Cost: $2.1 million
General Contractor: Stanek Constructors Inc
Start Date: August 2002
Completion Date: December 2005
Construction of a new masonry building to house the owner-furnished Trident treatment units and soda ash-free system and installation of an above-ground diesel tank.
Top

11. Woodmen WTP Upgrade 2002
Location: Woodmen
Cost: $1.9 million
General Contractor: Stanek Constructors Inc
Start Date: November 2002
Completion Date: March 2003
Upgrade of water filtration plant includes reservoir work one-half mile of 16-in force main new pump station.
Top

12. Great Western Reservoir Dam Rehabilitation
Location: Broomfield
Cost: $1.1 million
General Contractor: ASI RCC Inc
Start Date: December 2002
Completion Date: July 2003
Clearing of 18 acres for construction of new 55,000-cu-yd spillway and 85,000-cu-yd stability berm from onsite borrow sources, install 1,300 ln ft of 36-in. reinforced concrete pipe and three precast concrete manholes, rehabilitation of 590 ln ft of outlet works and toe drain pipe. Replacement of three existing outlet gates.
Top


 Click here for more Top Projects >>


 


Sponsors

© 2009 The McGraw-Hill Companies, Inc.
All Rights Reserved