1. Our Lady of Loreto Catholic
Parish
Location: Foxfield
Cost: $12 million
General Contractor: JHL Constructors Inc
Architect: David Owen Tryba
Start Date: August 2001
Completion Date: April 2003
$12 million new Catholic parish facility
Top
2. Centennial Community Church
Location: Centennial
Cost: $5.1 million
General Contractor: RAS Builders
Architect: Larson Group
Start Date: May 2002
Completion Date: February 2003
The 48,000-sq-ft addition consists of a new worship center, classrooms
and lobby hub with atrium.
Top
3. Franktown Seventh Day Adventist
Church
Location: Franktown
Cost: $1.6 million
General Contractor: MW Golden Constructors
Architect: Architectural Workshop LLC
Start Date: November 2002
Completion Date: June 2003
A new church consisting of 12,750 sq ft, including classrooms, fellowship
hall, office, storage, kitchen and sanctuary along with related site development
of landscaping, parking and utilities.
Top
|